MANAGEMENT PLAN

 

 Project Organization

The Project will be directed by the Yucca Corridor Coalition of Property Owners and Managers in consultation with the various City agencies involved in the rehabilitation process. Landscape will be conducted and supervised by the Hollywood Beautification Team in consultation with the Landscape Architect. Construction components will be let on bid and will be overseen by a Project Coordinator.

Costs-  t.b.a

Schedule

                    Groundbreaking is scheduled for October 2, 2000 with completion date target of September 30, 2001.